Forced Front Office Entry

32 of our schools are undergoing construction modifications to direct visitors through the front office area upon entry to the building. The district accelerated work on these projects while schools were closed due to pandemic.

There are two phases to the project. We anticipate most of the schools involved in this first phase to be completed by August 2020. 

The second phase of the project will involve the hardening of entrances for the remainder of our schools. We anticipate the completion of this phase by the end of the 2020-2021 school year.

Below, you will see two blueprints that include the demolition of the current entryway of a typical school and the completed plan for rerouting traffic through the front office area.

Before

Demolition Plan

After

New Floor Plans